Supplier capacity

How hard each supplier is running, read from 7 sources every morning

Short of our need2suppliers
Tight, inside the range2suppliers
Open PO value at risk$4.80M
Suppliers monitored214
SupplierOperating capacity vs our needOpen POsStatus
82% ± 3need 88%
$3.42MShort
76% ± 5need 83%
$1.38MShort
87% ± 2need 86%
$0.96MTight
89% ± 3need 90%
$0.52MTight
91% ± 4need 74%
$1.14MHas room
95% ± 2need 70%
$0.69MHas room
84% ± 6need 72%
$0.41MHas room
97% ± 1need 60%
$0.18MHas room

Keystone Castings

Castings and forgings · Erie, PA

Short
Operating at82%
Variance± 3%
Our need, 8 weeks88%
Gap to our need−6 pts
Operating capacityRange, ±3%Our need
50%60%70%80%90%100%W35W37W39W41W43W45W47W49W51Outlook

How we got to 82%

Five sources agree within 3 points. Their weekly pour schedule would bring this to ±1%.

SignalEffectSource
On time to promised date71% over 8 weeks, down from 93%−7 ptsSAP · goods receipts
Furnace 2 offline for reliningBack Dec 1, per their plant manager−4 ptsOutlook · supplier email
Promised lead time+12 days on confirmations since W40−3 ptsAriba · order confirmations
Shipped against ordered quantity88% of ordered pieces on ship notices−3 ptsAriba · ship notices
Quality notifications2 open on stage 1 nozzle castings−1 ptsSAP QM · notifications
Operating capacity82% ± 3

What it puts at risk

3 open POs need this supplier in the next 8 weeks

PONeed byLikelyImpact
450087120424 × Stage 1 nozzle castingNov 20Dec 4Unit GT-214 build slips 6 days
450087137716 × Transition piece castingNov 27Dec 8Uses 4 of 6 days of float
450087201540 × Exhaust frame strutDec 11Dec 14Covered by stock on hand

What Aerium suggests