Supplier capacity
How hard each supplier is running, read from 7 sources every morning
Short of our need2suppliers
Tight, inside the range2suppliers
Open PO value at risk$4.80M
Suppliers monitored214
| Supplier | Operating capacity vs our need | Open POs | Status |
|---|---|---|---|
82% ± 3need 88% | $3.42M | Short | |
76% ± 5need 83% | $1.38M | Short | |
87% ± 2need 86% | $0.96M | Tight | |
89% ± 3need 90% | $0.52M | Tight | |
91% ± 4need 74% | $1.14M | Has room | |
95% ± 2need 70% | $0.69M | Has room | |
84% ± 6need 72% | $0.41M | Has room | |
97% ± 1need 60% | $0.18M | Has room |
Keystone Castings
Castings and forgings · Erie, PA
Short
Operating at82%
Variance± 3%
Our need, 8 weeks88%
Gap to our need−6 pts
Operating capacityRange, ±3%Our need
How we got to 82%
Five sources agree within 3 points. Their weekly pour schedule would bring this to ±1%.
| Signal | Effect | Source |
|---|---|---|
| On time to promised date71% over 8 weeks, down from 93% | −7 pts | SAP · goods receipts |
| Furnace 2 offline for reliningBack Dec 1, per their plant manager | −4 pts | Outlook · supplier email |
| Promised lead time+12 days on confirmations since W40 | −3 pts | Ariba · order confirmations |
| Shipped against ordered quantity88% of ordered pieces on ship notices | −3 pts | Ariba · ship notices |
| Quality notifications2 open on stage 1 nozzle castings | −1 pts | SAP QM · notifications |
| Operating capacity | 82% ± 3 |
What it puts at risk
3 open POs need this supplier in the next 8 weeks
| PO | Need by | Likely | Impact |
|---|---|---|---|
| 450087120424 × Stage 1 nozzle casting | Nov 20 | Dec 4 | Unit GT-214 build slips 6 days |
| 450087137716 × Transition piece casting | Nov 27 | Dec 8 | Uses 4 of 6 days of float |
| 450087201540 × Exhaust frame strut | Dec 11 | Dec 14 | Covered by stock on hand |